At Xiahewan Station, workers are currently carrying out the main structure construction. Xiahewan Station is the first station of Metro Line 6 train to enter Sujiatun District.
At present, its main structure construction is being pushed forward. Moreover, efforts are being made to complete the capping of the main structure by December and achieve the start of tunneling by the Chinese New Year.
At the construction sites of Xuesonglu Station, Shaliulu Station and Yingchunjie Parking Lot access line, the main construction operations such as reinforcement binding and concrete pouring are being carried out in full swing.
Up to now, the main structure of Xuesonglu Station has been completed at 20%, the main structure of Shaliulu Station has been completed at nearly 10%, and at the Yingchunjie Parking Lot access line, the main construction is about to be carried out for the open excavation section.
At the Kuisonglu Station, the main body of the station has been capped, the back-filling of soil above the roof plate has been completed at nearly 70%, the removal of steel supports has been completed at 90%, and the shield tunneling construction of the left line is being pushed forward.
The Shenyang Metro Line 6 starts from Yalujiangbeijie Station in the north and ends at Shaliulu Station in the south, with a total length of 35 kilometers and 29 stations. It is another north-south transportation artery in the network.
Metro Line 6 will extend to the core area of Sujiatun District in the future, and the first transfer station between Metro Line 6 and Metro Line 10 Phase II will be located in this district, which will greatly facilitate the travel of citizens and further drive the economic development along the line.