On March 29, after 9 days of round-the-clock job, the first phase of the emergency renovation project of Shenyang makeshift hospital was successfully completed and officially ready for delivery and use.
The total construction area of the emergency project of the makeshift hospital is about 51,000 square meters.
It is reconstructed in two phases.
The construction area of the first phase is 31,000 square meters, which can provide 1,000 treatment beds and a medical material warehouse of 13,000 square meters.
The construction area of the second phase is 20,000 square meters, which can provide another 1,000 treatment beds after the renovation is completed.
The renovation of the makeshift hospital is based on the principle of "three areas and two passages", and the makeshift hospital is divided into functional areas according to clean area, semi-clean area and polluted area.
The project was officially launched on the evening of March 20.
The first phase of the project has been completed and the delivery conditions have been met.
For some areas completed in advance, the docking work has already been undertaken by the Sixth People's Hospital of Shenyang, the receiving unit of the makeshift hospital.
The second phase of the renovation project of the makeshift hospital is currently progressing smoothly.
At the same time, in the south parking lot of Shenyang International Exhibition Center not far from the south side of the makeshift hospital, over 10,000 builders are working round-the-clock.
The emergency project of Shenyang health station is under continuous construction.
The total construction area of the health station is 145,000 square meters.
After completion, about 5,000 beds of temporary centralized quarantine capacity can be added.